Construction
- January 2002: Building permit application for Dischmatal and Strelapass
- March 2002: Decision for the site in Dischmatal
- April 2002: Building permission
- June 2002: Construction work: Vault, Pile foundation, Telephon line
- July 2002: Installation of the technical devices; starting of the operation and data transmission to SED Zürich
- August 2002: Installation of the satellite link to Vienna
- September 2002: Starting of the CTBTO computer and data transmission to Vienna
- July 2003: Completing of the definitive devices configuration