EN

Construction

  • January 2002: Building permit application for Dischmatal and Strelapass
  • March 2002: Decision for the site in Dischmatal
  • April 2002: Building permission
  • June 2002: Construction work: Vault, Pile foundation, Telephon line
  • July 2002: Installation of the technical devices; starting of the operation and data transmission to SED Zürich
  • August 2002: Installation of the satellite link to Vienna
  • September 2002: Starting of the CTBTO computer and data transmission to Vienna
  • July 2003: Completing of the definitive devices configuration
Site of the vault for the seismometer
Site of the vault Site of the vault Site of the vault3 Site of the vault
Ditch for the Telephone and power line
Telephone and power line Telephone and power line Telephone and power line Telephone and power line
The interior of the SLF Hut whith the communication device and VSAT antenna
SLF Hut Interior
Cover of the box whith the VSAT
Cover VSAT Box
Helicopter transporting the VSAT box
Helicopter Transport Helicopter Transport